Crystal Bridge Replacement
Road Closure

NOTICE : Bridge Key 33038 - Bridge Replacement at 1000 S (Crystal Ave) Bridge will be replaced with a new premanufactured steel bridge and Cast-In-Place abutment system. Work will begin after Sept 1st, closing 1000 S ( Crystal Ave) to through traffic and must be completed within 75 working days of starting construction. Once started, work must continuously progress until completion, except for paving. If all project structure and roadway work items are complete, and weather does not permit project 405 paving to occur within the specification requirements, time may be suspended by the Engineer until weather allows.
Depending on weather limitations, paving may be delayed until spring, April 1, 2026. Please see the attachment for detour mapping.
This project is being guided by Idaho Transportation Department Specifications and Forsgren Engineering.